Transportation terminal at 8329 Esquesing Line approved by Milton Council on December 8, 2025

Ten months after it was filed, a rezoning for a transportation terminal on the east side of Esquesing Line, north of James Snow Parkway, was approved. Council passed two by-laws, one for each of the Town's zoning by-laws.

MiltonIQ Newsroom4 sources · 2 min read

Email

The details

What Council decided

On December 8, 2025, Milton Council approved a zoning application by 2369219 Ontario Inc. for 8329 Esquesing Line (file Z-02/25). Resolution 174-25, moved by Councillor Challinor and seconded by Councillor Malboeuf, approved amendments to both of the Town's comprehensive zoning by-laws, the urban By-law 016-2014 and the rural By-law 144-2003, on the recommendation of technical report DS-066-25. The motion carried. At the end of the meeting Council passed the two implementing by-laws, 103-2025 and 104-2025.

What was applied for

The Town's notice of the application, dated February 21, 2025, places the property on the east side of Esquesing Line, north of James Snow Parkway. The owner applied to allow a transportation terminal with a building of about 1,200 square metres. The front part of the land was to move from a Future Development zone to a site-specific General Industrial (M2) zone, with a strip rezoned Greenlands A to create an environmental buffer beside the watercourse that crosses the site.

8329 Esquesing Line (Town notice, Feb. 21, 2025, and Council minutes)
Owner and applicant
2369219 Ontario Inc.
Town file
Z-02/25
Location
East side of Esquesing Line, north of James Snow Parkway
Proposed use
Transportation terminal with a building of about 1,200 square metres
Zoning sought
Future Development to site-specific General Industrial (M2), with a Greenlands A buffer along the watercourse
Public meeting
March 17, 2025 (report DS-017-25)
Approved
December 8, 2025 (Res. 174-25); By-laws 103-2025 and 104-2025

How the file moved

The applicant supported the filing with a traffic brief, a comprehensive environmental site servicing study, a photometric plan and a topographic survey, the notice says. Council held the statutory public meeting on March 17, 2025, and received the initial report for information; the minutes do not record any member of the public speaking. In the fall, the Town commissioned a peer review for the file: Council's November 3, 2025 purchasing report records an assignment awarded to WSP Canada Inc. for $53,653, before HST, under delegated authority. The approval followed five weeks later.

Where it stands

The rezoning is approved. A zoning approval is not a building permit; further Town approvals, such as site plan approval, typically follow before construction. As of November 9, 2026, MiltonIQ could not confirm from the Town's published pages whether the by-laws were appealed or whether work on the site has begun.

The decision is part of a run of truck-related approvals in Milton's employment lands. In February 2025, Council allowed a commercial truck dealership at 7265 No. 5 Side Road, and in September 2026 it approved a truck terminal there and a warehouse and transportation terminal at 7072 Sixth Line.

Sources

Every factual claim above traces to one of these documents.

  1. Town of Milton

    Council Meeting - December 8, 2025 (Minutes)

    Published December 8, 2025 · Retrieved November 9, 2026

  2. Town of Milton

    Notice of Zoning By-law Amendment Application & Statutory Public Meeting: 8329 Esquesing Line

    Published February 21, 2025 · Retrieved November 9, 2026

  3. Town of Milton

    Council Meeting - March 17, 2025 (Minutes)

    Published March 17, 2025 · Retrieved November 9, 2026

  4. Town of Milton

    Council Meeting - November 3, 2025 (Minutes)

    Published November 3, 2025 · Retrieved November 9, 2026

Spotted an error? We keep the URL, update the timestamp and record the change. Our corrections policy.


Go deeper

All stories