Milton's $57.8-million construction year: what is scheduled this fall
The Town of Milton is spending $57.8 million on roads, bridges and stormwater work in 2026. Resurfacing and the Appleby Line work run through the fall, Nipissing Road and Childs Drive continue into 2027, and major Fifth Line work is planned to start in 2027.
The 2026 program
The Town of Milton announced in May that it is investing $57.8 million in infrastructure projects through 2026. The work ranges from road reconstruction, resurfacing and intersection improvements to new bike lanes, more sidewalks, curb and gutter upkeep, storm sewer repairs and bridge maintenance. The Town's 2026 Projects page says the total reflects the 2026 approved budget, and that some projects being completed this year were approved in earlier budgets.
The Town warns residents to expect road closures and lane restrictions on both main arterial roads and residential streets, and says it coordinates timing with Halton Region and private-sector work where it can. Residents directly affected by a project are to receive notice before construction starts.
Still running this fall
- Asphalt replacement with localized curb, gutter and sidewalk repairs; May through fall 2026
- Urbanization, drainage improvements, localized retaining walls and traffic calming; May through fall 2026
- Retaining wall reconstruction; planned for summer and fall 2026
- Nipissing reconstruction and Childs Drive widening from Ontario Street to Nipissing Road; under way, expected complete fall 2027
- Utility relocations in 2026 ahead of widening and urbanization; major construction planned from 2027 over multiple years
The Nipissing Road and Childs Drive project includes road widening, urbanization, a sidewalk, a multi-use pathway and additional turning lanes. On Fifth Line, the 2026 utility work is preliminary: the Town says the major widening will run over several years once it begins.
Other 2026 work
- The Expanded Asphalt Program on First Line Nassagaweya and No. 2 Side Road, with asphalt rehabilitation and paved-shoulder improvements, was scheduled for June through September.
- Traffic calming and raised crosswalks near schools and on collector roads, including speed cushions, were scheduled for July and August.
- Smaller jobs on the list, scheduled for spring and summer, include Morobel Drive and Pearl Street drainage work, a guiderail replacement program, Thompson Road path improvements and signals at Esquesing Line and No. 5 Side Road, a joint project with Halton Hills.
Next on the list: Sixth Line
Separately, the Town is studying Sixth Line from Britannia Road to Highway 401 through a Schedule C Municipal Class Environmental Assessment, building on its 2024 Transportation Master Plan Update, which identified a need for transportation improvements in northeast Milton. The first online engagement opened in April 2026. The project page lists a second public engagement as tentative for November 2026 and study completion as tentative for April 2027.
Sources
Town of Milton
2026 ProjectsTown of Milton
Sixth Line Municipal Class Environmental Assessment