Eight apartment buildings of 10 to 15 storeys approved at Britannia Road and Regional Road 25 in May 2024
Milton Council rezoned Mattamy land on the west side of Regional Road 25, north of Britannia Road, for eight residential buildings with ground-floor shops. Two of three holding conditions were lifted for the first two phases in April 2025.
The details
What Council approved
On May 13, 2024, Milton Council approved a zoning by-law amendment for land at the northwest corner of Britannia Road and Regional Road 25, applied for by Mattamy (Milton West) Limited under a file first opened in 2018 (Z-02/18). The resolution, 070-24, approved staff report DS-043-24 "to facilitate the development of eight mixed-use and residential apartment buildings," and Council passed By-law 042-2024 the same night.
According to the Town's notice of passing, the by-law places the land in a site-specific Mixed Use zone (MU*351) and permits eight residential buildings ranging from 10 to 15 storeys, with 920 square metres of ground-floor commercial space. It sets site-specific rules for building heights, setbacks, parking and density. The notice's key map shows the site as two blocks on the west side of Regional Road 25, one on each side of Etheridge Avenue; a later Town notice gives the address as 6046 to 6056 Regional Road 25. The area is in Milton's Ford neighbourhood, where staff reports call the project Mattamy Framgard.
- Mattamy (Milton West) Limited
- Z-02/18 (rezoning); SP-04/24 (site plan); Z-26/24 (holding removal)
- West side of Regional Road 25, north of Britannia Road, on both sides of Etheridge Avenue
- Eight residential buildings, 10 to 15 storeys
- 920
- Mixed Use MU*351 with holding symbols H83, H84 and H85 (By-law 042-2024)
- May 13, 2024 (Res. 070-24)
- H83 and H85, for the Phase I and II lands, on April 28, 2025 (By-law 049-2025)
At the meeting
Two people addressed Council about the report, according to the minutes. The motion carried; the minutes do not record a count. As with other large housing approvals in this period, the resolution sent the report to the provincial Ministers of Health, Education, Transportation and Infrastructure and to Metrolinx, with a request to review and plan for future Milton District Hospital, school and transportation expansions. The last day to appeal the by-law was June 4, 2024.
What has happened since
The by-law tied development to three holding symbols. On April 7, 2025, the Town gave notice (file Z-26/24) that staff were satisfied the conditions of two of them had been met for the Phase I and II lands. Holding 83 required the applicant to secure servicing allocation, confirmed by Halton Region, for the phases proposed. Holding 85 required an updated transportation impact study, a wind study and a site plan application. Council passed By-law 049-2025 on April 28, 2025, removing both for those phases, which the notice said would let the applicant proceed to site plan approval.
Neither notice says what Holding 84 requires, and the notices do not show the holding symbols being lifted for any later phase. As of November 9, 2026, MiltonIQ could not confirm from the Town's published pages whether site plan approval has been granted or construction has started.
Sources
Town of Milton
Council Meeting - May 13, 2024 (Minutes)Town of Milton
Notice of Passing: Zoning By-Law Amendment 042-2024Town of Milton
Council Meeting - April 28, 2025 (Minutes)