Milton's Stormwater Master Plan: begun in fall 2024, due in winter 2027, and focused first on rural ditches and culverts
The Town announced the study on October 11, 2024 and began it as a formal environmental assessment that December. A first open house was held in Campbellville in April 2026. The plan will rank the drainage projects Milton needs.
The details
What the Town started
On October 11, 2024, the Town of Milton announced that it was creating a Stormwater Management Master Plan, a comprehensive strategy for managing the rain and snowmelt that runs off streets and properties into creeks and, eventually, the Great Lakes. On December 19, 2024, it issued a formal notice of study commencement, placing the work under Ontario's Municipal Class Environmental Assessment process.
The Town set out five purposes for the plan:
- Develop a short- and long-range stormwater strategy for Milton.
- Consider the implications of climate change.
- Manage risks to life, property and the natural environment.
- Recommend updates to stormwater policy and guidelines.
- Identify and rank the projects needed to improve stormwater management.
The commencement notice adds that the study will assess the Town's existing stormwater infrastructure, identify vulnerabilities and account for the combined effects of climate change and future development. It will also fold in new provincial requirements, including the Consolidated Linear Infrastructure Environmental Compliance Approval issued by the Ministry of the Environment, Conservation and Parks. When complete, the Town says, the plan will serve as a decision-making guide for prioritizing, estimating and budgeting projects.
What crews have been looking at
The first part of the project is field work, and the Town's project page says it is focused on rural Milton. The studies are meant to show where maintenance can improve the performance of ditches, culverts and areas that have flooded. Residents may have seen people examining roadside ditches, culverts under roads and driveways, Town drainage easements, areas with frequent flooding, areas with beaver activity and low impact development facilities, which treat stormwater at its source.
Timeline
Done: Project begins
Fall 2024. Announced October 11; notice of study commencement December 19, 2024.
Done: Field studies and analysis
Fall 2024 to winter 2025.
Done: Public Open House #1
Held April 29, 2026 at the Nassagaweya Tennis Centre and Community Hall, 9267 Guelph Line, Campbellville; online survey to May 29, 2026.
Now: Stormwater strategy
Development and analysis, spring 2026 to winter 2026.
Next: Final reporting and completion
Winter 2026 to winter 2027, followed by a 30-day public review of the environmental assessment.
The Town's announcement of the April 2026 open house said the project team would present the study's goals, its field work and the conditions affecting stormwater management, with staff and consultants on hand for questions. The presentation from that evening is posted on the project's Let's Talk Milton page.
How to follow it or comment
The Town says it will hold further public open houses and share details closer to the dates; as of November 9, 2026, its project page does not list one. Comments can be posted to the feedback forum on the project's Let's Talk Milton page, where the Town also says it will post documents for review, and residents can subscribe there to project updates. The environmental assessment that documents the study's results will be released for a 30-day public review before the plan is final.
Sources
Town of Milton
Town initiates Stormwater Management Master PlanTown of Milton
Stormwater Master PlanTown of Milton
Public invited to learn about stormwaterTown of Milton
Stormwater Management Master Plan (Let's Talk Milton)