Eight-storey long-term care home approved at 6360 and 6382 Regional Road 25 in March 2024

Milton Council rezoned two properties on the west side of Regional Road 25 for an eight-storey long-term care home with shops and offices at ground level. A provincial licensing record describes a 192-bed home at the address.

MiltonIQ Newsroom4 sources · 2 min read

Email

The details

What Council approved

On March 4, 2024, Milton Council approved a zoning by-law amendment for 6360 and 6382 Regional Road 25, two adjoining properties on the west side of the road. The applicant was a numbered company, 2376439 Ontario Inc., and the Town file is Z-11/23. Resolution 025-24 approved staff report DS-011-24 "to facilitate the construction" of an eight-storey long-term care facility with ground-floor commercial space, and Council passed By-law 016-2024 at the same meeting.

The Town's notice of passing says the by-law changed the land from a Future Development zone to a Mixed Use zone with site-specific provisions, for an eight-storey long-term care home with retail and office space on the ground floor. The key map published with the notice shows the site fronting Regional Road 25, with Restivo Lane and Sheaffe Place behind it to the west. The last day to appeal was March 26, 2024.

6360 and 6382 Regional Road 25
Applicant
2376439 Ontario Inc. (Town notice)
Town files
Z-11/23 (rezoning); Z-13/24 (holding removal)
Approved use
Eight-storey long-term care home with ground-floor retail and office space
Zoning
Future Development to site-specific Mixed Use (By-law 016-2024)
Council decision
March 4, 2024 (Res. 025-24)
Holding provision H90
Town notice of July 11, 2024 set its removal for August 1, 2024
Beds
192, according to the Ministry of Long-Term Care's licensing registry

The holding condition

The zoning came with a holding provision, H90, which stops development until its conditions are met. On July 11, 2024, the Town gave notice (file Z-13/24) that staff had found the conditions satisfied: a letter of reliance for the Phase 1 and Phase 2 environmental site assessments, to the satisfaction of the Town and Halton Region, and an updated transportation impact study and parking report. Because Council has delegated holding removals to the Commissioner of Development Services, the notice said the amending by-law would be passed on August 1, 2024, allowing development of the lot to proceed.

What the Province's records say

The Town's notices describe the building but not its size in beds or who would run it. The Ministry of Long-Term Care's public registry of licensing proposals does. It lists Project #22-044, a proposal from Excelligent Care for a licence for "Careswell Residences - Milton," described as a new 192-bed long-term care home proposed at 6360 Regional Road 25. The registry says the proposal involves 192 beds allocated by the ministry and a new licence of up to 30 years once the home is developed. The consultation on it is listed as closed; the entry does not show a decision.

Where it stands

The Town's part is done: the land is zoned for the home and, by the Town's own notice, the holding provision was to come off in August 2024. What MiltonIQ could not confirm from a Town or provincial document, as of November 9, 2026, is whether construction is under way, when the home is expected to open, or under what name. Those details are left out of this record rather than taken from other sources.

Sources

Every factual claim above traces to one of these documents.

  1. Town of Milton

    Council Meeting - March 4, 2024 (Minutes)

    Published March 4, 2024 · Retrieved November 9, 2026

  2. Town of Milton

    Notice of Passing: Zoning By-law Amendment 016-2024

    Published March 7, 2024 · Retrieved November 9, 2026

  3. Town of Milton

    Notice of Intent: To Pass Amending By-Law to Remove a Holding Provision - Z-13/24

    Published July 11, 2024 · Retrieved November 9, 2026

  4. Province of Ontario

    Ontario's long-term care licensing public consultation registry

    Retrieved November 9, 2026

Spotted an error? We keep the URL, update the timestamp and record the change. Our corrections policy.