Britannia's transportation plan, completed in April 2026, is sized for 57,500 residents and warns that intersection upgrades alone will not be enough

The Town issued its notice of study completion on April 1, 2026 for a new transportation master plan covering the Britannia Secondary Plan area. It forecasts 11,600 car trips in the afternoon peak hour and prices the local network at about $182 million.

MiltonIQ Newsroom2 sources · 3 min read

Email

The details

What was completed

On April 1, 2026, the Town of Milton issued a notice of study completion for a transportation master plan for the Britannia Secondary Plan area. The plan, prepared by the consulting firm WSP and dated December 2025, completes the first two phases of the Municipal Class Environmental Assessment process. Its job, the notice says, is to guide spending on roads, transit, cycling and walking and to reserve wide enough rights-of-way for the future road network. The notice opened a 30-day public review that ran to April 30, 2026.

It replaces a plan written for the same area in 2022. Since then, the Town says, the population and employment forecasts have risen and the planning horizon has moved from 2031 to 2051.

The area and the forecast

The Britannia Secondary Plan area is mostly farmland in south Milton, about 6.5 kilometres south and east of the old town centre, southeast of Boyne and west of the Trafalgar corridor. Britannia Road, Thompson Road South, Third Line, Fourth Line, James Snow Parkway, Fifth Line and Sixth Line bound or cross it. The plan notes that no transit route serves the area today and that, apart from a multi-use path on Britannia Road, it has no sidewalks or cycling facilities.

What the Britannia transportation plan assumes at full build-out, from Tables 0.2 and 0.3
Population
About 57,500
Jobs
About 9,300
Homes in neighbourhoods
14,140units, including 6,830 detached and semi-detached and 6,630 townhouses of all kinds
Homes in mixed-use areas
3,340units
Schools
16: 13 elementary and three secondary
Parks
11, including four district parks
Car trips generated
7,810 in the morning peak hour and 11,602 in the afternoon peak hour
Share of trips not by car
33 per cent, which the plan calls aspirational
Estimated cost of the local network
About $182.45 million over two phases

What it recommends

  • Roads: a network of collector roads through the new neighbourhoods, plus extra northbound lanes at the Britannia Road intersections with Thompson Road and Fifth Line, with room protected now for double left-turn lanes at other intersections.
  • Cycling and walking: separated bike lanes or cycle tracks on every collector road and on James Snow Parkway, a separated lane on Lower Base Line, and a trail network that is still conceptual.
  • Transit: Milton Transit extended onto the area's arterial and collector roads, feeding trunk routes on Regional Road 25, Britannia Road, James Snow Parkway and Trafalgar Road.
  • Phasing: neighbourhoods east of Fourth Line first, so traffic can be reassessed before the second phase.
  • Follow-up: a road safety strategy and a travel-demand plan for the area, with staff assigned to run it.

The plan's central finding is uncomfortable. In the 2051 forecast, none of the intersections analysed operates below the volume-to-capacity ratio of 0.85 that Halton Region uses as its threshold, and a test that cut background traffic from the rest of Milton by 15 per cent improved every intersection but still left many over capacity. The consultants conclude that intersection improvements alone will not be sufficient, and recommend Town-wide efforts to reduce car volumes through transit, cycling, working from home, carpooling and putting jobs closer to homes.

The $182.45 million estimate covers collector roads, intersection work, creek crossings, trails and added transit service. It leaves out projects already in other plans: the James Snow Parkway and Louis St. Laurent Avenue extensions, the widening of Britannia Road and James Snow Parkway, and Town work on Fifth Line and Sixth Line. Under the Town's local service policy, collector roads are the developers' direct responsibility. Halton Region is separately carrying out an environmental assessment for what the plan calls the New North Regional Road.

Where it stands now

As of November 9, 2026, the Town's Britannia page says the transportation master plan was completed as part of the secondary plan, that the notice of study completion has been issued, and posts the final document. Council approved the Britannia Secondary Plan on January 27, 2025 and it came into force on March 3, 2025.

No houses can be approved yet. The Town says a tertiary plan, prepared by the landowners, must be submitted and endorsed by Council before any development application in Britannia is approved, and the transportation plan sets out the traffic study that tertiary plan must include: new counts, confirmed road classes and widths, intersection designs, and a justified estimate of how many trips will really be made without a car.

Sources

Every factual claim above traces to one of these documents.

  1. Town of Milton

    Notice of Study Completion: Transportation Master Plan for the Britannia Secondary Plan

    Published April 1, 2026 · Retrieved November 9, 2026