Transit

Milton's transportation plan to 2051, finalized in May 2025: four-lane Sixth Line, a Main Street extension to Trafalgar and 271 km of cycling and walking routes

The Town finalized its Transportation Master Plan Update on May 5, 2025, five months after Council endorsed it. It plans for 400,000 residents, lists a dozen Town road projects and has already led to the Sixth Line study.

MiltonIQ Newsroom7 sources · 3 min read

Email

The details

What was finalized

On May 5, 2025, the Town of Milton announced that it had finalized its Transportation Master Plan Update, a plan for walking, cycling, transit and driving to 2051. Council had endorsed the recommendations on December 9, 2024 and approved the update in principle, subject to a 30-day public review required under the Municipal Class Environmental Assessment process. The Town said that review ended on January 31, 2025 and that staff revised the document before posting the final version.

The update was prepared with the consulting firm WSP and builds on the Town's 2018 plan. It assumes Milton grows from about 135,000 people in 2021 to about 400,000 in 2051, and the Town describes it as a living document reviewed every five years.

The road projects

The plan lists 12 improvements to Town roads, grouped as short, medium and long term, with short term meaning by 2031. Improvements to Regional roads are left to Halton Region's own studies. The costs below are the plan's high-level totals, including design and contingency, and exclude land, bridges and crossings.

Larger Town road projects in the Transportation Master Plan Update (Tables 25 and 29)
Main Street East, Fifth Line to Trafalgar Road
New four-lane extension, 2.76 km, short term, about $48.0 million
Sixth Line, Highway 401 to Britannia Road
Widen from two to four lanes, 5.61 km, short term, about $65.5 million
Louis St. Laurent Avenue, Fifth Line to Sixth Line
New four-lane extension, 1.41 km, short term, about $20.6 million
Louis St. Laurent Avenue, Sixth Line to Trafalgar Road
New four-lane extension, 1.35 km, long term, about $20.6 million
Ontario Street South, Derry Road to Main Street East
Convert two lanes to high-occupancy vehicle lanes, 1.84 km, short term, not costed
Britannia Road, Tremaine Road to the Education Village's west boundary
Widen from two to four lanes, 0.42 km, medium term, about $4.1 million
Lower Base Line, Fourth Line to Fifth Line
New two-lane extension, 1.96 km, medium term, about $9.3 million
Lower Base Line, Fifth Line to the Town's east boundary
Widen from two to four lanes, 4.93 km, long term, about $48.3 million
Sixth Line, Britannia Road to Lower Base Line
Widen from two to four lanes, 3.14 km, long term, about $30.7 million

The other three are short new streets around Milton GO Station, meant to break up large blocks as the station area redevelops; two of them are developers' responsibility. The plan also costs turn-lane additions at a series of intersections on Main Street East, Ontario Street and Thompson Road.

Transit, cycling and the rest

  • Transit priority corridors: Thompson Road from Main Street East to Derry Road in the short term, and Bronte Street and Main Street East in the long term. The plan leaves route planning to Milton Transit's five-year service plan.
  • GO service: continued support for two-way, all-day trains on the Milton line, redevelopment of Milton GO Station for more bus capacity, and a new Trafalgar/Agerton GO station as a future transit hub.
  • Walking and cycling: a network of 271.3 km of trails, bike lanes and paved shoulders, up from 233.6 km in the 2018 plan, built on a Complete Streets approach.
  • Trucks: better management and communication of truck routes, co-ordinated with neighbouring municipalities.
  • Safety and parking: a road safety strategy backed by Official Plan policies, and a parking study.
  • Demand management: a strategy to cut single-occupant car trips, with carpool incentives, smart parking management and transit discounts.

The plan is candid about limits. It says some congestion will have to be tolerated at peak hours in places where widening roads would damage the surroundings or crowd out other ways of travelling.

What has followed

A master plan approves nothing by itself; each project still needs its own study and budget. Several steps since trace back to this one. The Town is carrying out a Schedule C environmental assessment of Sixth Line from Britannia Road to Highway 401 that, the Town says, builds on the update. The 2026 budget funds a Complete Street Design Manual, one of the plan's recommendations. And the transportation plan completed for the Britannia Secondary Plan area in April 2026 counts the Main Street East and Louis St. Laurent Avenue extensions as part of the planned network.

As of November 9, 2026, the Town's Transportation Master Plan page still presents the 2024 update, with its full report and appendices, as the plan in force. The Town says it updates the plan every five years.

Sources

Every factual claim above traces to one of these documents.

  1. Town of Milton

    Town of Milton transportation vision outlined in updated Master Plan

    Published May 5, 2025 · Retrieved November 9, 2026

  2. Town of Milton

    Milton's Updated Transportation Master Plan (rider alert)

    Published May 6, 2025 · Retrieved November 9, 2026

  3. Town of Milton

    Budget Highlights

    Retrieved November 9, 2026