Landowners will front $2.2 million so Milton can plan 438 hectares of employment land along Tremaine Road
On June 22, 2026, Milton Council approved a funding agreement with the Tremaine Employment Corridor Landowners Group to pay up front for the studies behind a Town-led Tremaine Secondary Plan south of Britannia Road.
The details
What Council decided
On June 22, 2026, Milton Council authorized the Mayor and Town Clerk to sign a funding agreement with Tremaine Employment Corridor Landowners Group Inc. The agreement lets the Town carry out a Town-initiated Official Plan amendment, the Tremaine Secondary Plan, and its supporting studies for employment lands around Tremaine Road south of Britannia Road, with the landowners paying the costs as the work proceeds. Council also delegated authority to the Commissioner of Development Services to amend the agreement, and moved eight study projects that the 2025 development charge background study had placed beyond its forecast period into the 2026 capital budget.
- About 438 hectares (1,081 acres)
- Southwest Milton: east of Bell School Line, west of the CN rail line, south of Britannia Road along Tremaine Road to north of Lower Base Line West
- Employment; identified as a New Economic Growth Area in the Town's Official Plan
- First identified in Halton's Sustainable Halton Plan (ROPA 38), extended in ROPA 49, then brought into Milton's Official Plan through OPA 92
- $2,212,003, including about $1,590,600 for outside consultants
- The landowner group, through a trustee holding securities
- The Town, from a future development charge or other charge, once collected
What will be studied
- Water and wastewater servicing
- A functional servicing and environmental management strategy, covering stormwater
- A transportation plan
- A fisheries compensation plan
- The secondary plan itself
- A parks and open space study
- Urban design guidelines
- An update of the Indian Creek subwatershed study
How the arrangement works
Town policy requires an area-specific plan for the Tremaine lands before any private application there can be approved. The report says the landowners want planning to start as early as possible and offered to fund 100% of the work to spare the Town's cash flow. The Town is to run the program: writing the terms of reference, hiring consultants under its procurement rules and taking the amendment to Council. It will invoice the trustee as costs are incurred, and the landowners' consultants may sit on the steering and technical advisory committees. Before the Town-led process starts, the landowners agreed to begin key environmental background studies and fieldwork, with reasonable costs reimbursable if done to the Town's satisfaction.
Separately, a group of landowners including Canadian National Railway Company applied in August 2026 to bring about 240 hectares east of Tremaine Road, south of Britannia, into the urban area for an industrial park. That is a separate file, reported separately; the staff report on the secondary plan does not say how the two areas relate.
Where it stands now
As of November 11, 2026, the Town has not published terms of reference, a consultant award, a project page or a public meeting date for the Tremaine Secondary Plan, and no item on it appears in Council minutes through July 13, 2026 or on the September 14 agenda. When the report was written, staff and outside counsel were still finalizing the agreement's wording; whether it has been signed was not confirmed.